Map of Jammu and Kashmir, Ladakh, Himachal Pradesh and Punjab within India's boundary as per the Survey of India, showing the Chenab, India's hydropower projects on it (running, being built and planned), the planned Chenab-Beas tunnel, and Pakistan-occupied Kashmir (PoK) under Pakistan's illegal occupation.
Jammu And Kashmir · Geopolitics · 2 Nov 2026

The Dams India Is Building On The Chenab

Jammu And KashmirIndus Waters TreatyChenabHydropowerIndia PakistanLadakh

India put the Indus Waters Treaty in abeyance on 23 April 2025, after the terror attack at Pahalgam, until Pakistan credibly and irrevocably abjures its support for cross-border terrorism. Since then it has pushed ahead on the Chenab. Four projects with 3,014 MW between them are being built, Sawalkot (1,856 MW) is awaiting final approval, and NHPC has invited tenders for an 8.7 km tunnel to carry Chenab water into the Beas. On 31 August 2026 a Court of Arbitration that India does not recognise said the treaty remains in force and ordered limits on concreting at Ratle. India rejected it the same day. The map shows India’s boundary as drawn by the Survey of India, Pakistan-occupied Kashmir (PoK), Indian territory under Pakistan’s illegal occupation, and India’s projects on the Chenab.

3,014 MWbeing built on the Chenab and its tributary, the Marusudar
1,856 MWplanned at Sawalkot, awaiting final approval
135.6 MAFaverage yearly flow of the western rivers, against 32.8 MAF for the eastern rivers allotted to India for unrestricted use
8.7 kmtunnel planned to carry Chenab water into the Beas basin
Share This MapFree To Share With Credit: Tushar Gupta · politypolicy.com
How To Read It
  • India’s boundary is drawn as published by the Survey of India. Everything inside it is Indian territory; the green shading marks Pakistan-occupied Kashmir (PoK), under Pakistan’s illegal occupation.
  • The bright blue river is the Chenab, with the Chandra and Bhaga that form it in Himachal Pradesh and the Marusudar that joins it near Kishtwar. It flows west through Jammu and Kashmir and into Pakistan, as the arrow shows. Other rivers are in darker blue.
  • Every project marked is on the Chenab or the Marusudar. White circles are running, orange diamonds are being built, and the dashed diamond (Sawalkot) is planned. Each label gives the name, the capacity, the status and the type: run-of-river plants hold back only a little water; of the projects running or being built, Pakal Dul is the only storage project.
  • Four projects are clustered around Kishtwar, so their names are set out on lines. The red rings mark Ratle, where a Court of Arbitration at The Hague ordered limits on construction; India does not recognise the court.
  • The violet dash is the planned tunnel to carry Chenab water into the Beas basin, drawn approximately from the reported site near Koksar. India’s projects on the Jhelum and the Indus are listed in the table below. Site positions are approximate; capacities and progress are official figures.
Key
The Chenab And Its TributariesOther RiversDam RunningDam Being Built, Or Planned (Dashed)Planned Tunnel, Chenab Water To The BeasPakistan-Occupied Kashmir (PoK), Under Pakistan’s Illegal OccupationIndia’s Boundary (Survey Of India)
Why The Chenab Matters

A Treaty In Abeyance

On 23 April 2025, the day after the Pahalgam attack, India said the Indus Waters Treaty would be held in abeyance with immediate effect, until Pakistan credibly and irrevocably abjures its support for cross-border terrorism. India says that position remains in force.

Why These Dams Cannot Stop The Chenab

Almost all of India’s Chenab projects are run-of-river: they pass the river’s flow through turbines and hold back only a little water to balance power through the day. Of the projects running or being built, only Pakal Dul is a storage project, holding roughly 108 to 109 million cubic metres, about 0.09 MAF. That is less than 0.1% of the 135.6 MAF the western rivers carry in a year. The projects give India more power and more control over timing, not the ability to stop the river.

Four Projects, 3,014 MW

Pakal Dul (1,000 MW) and Kiru (624 MW) are over 80% built and due by December 2026. Kwar (540 MW) is due in 2028, and Ratle (850 MW) in November 2028, according to the government’s PAIMANA progress report.

Ratle And The Court

On 31 August 2026 a Court of Arbitration said the treaty remains in force and barred India from concreting parts of the Ratle dam wall and intake above certain levels until 90 days after a Neutral Expert gives a final decision, expected in July 2027. The Ministry of External Affairs called it an “illegally-constituted and so-called Court of Arbitration” whose pronouncements “will have no effect on India’s actions”.

Water Into The Beas

A planned 8.7 km tunnel under the Pir Panjal would carry surplus water from the Chandra, a Chenab tributary, into the Beas basin, with a 19 m barrage in the Lahaul valley. NHPC is also working on a tunnel to flush silt from the Salal reservoir. Together they cost about Rs 2,600 crore.

Tulbul, Revived

The Tulbul barrage below Wular Lake on the Jhelum was abandoned in 1987 after Pakistan objected. In June 2025 the Jal Shakti Minister said the government would study its project report before deciding.

What The Treaty Split

The western rivers carry about 135.6 million acre feet a year on average, against 32.8 MAF for the eastern rivers, according to the government. The eastern rivers are India’s to use in full; on the western rivers India was limited mainly to run-of-river power.

Every Large Project On The Chenab, And On The Jhelum And Indus

Projects above 25 MW. The first eight are on the map; the rest are on paper or on other rivers. Capacities from NHPC, JKSPDC and SJVN; progress from the PAIMANA report, July 2026; storage from the Power Minister (June 2025), Greater Kashmir (July 2025) and the Neutral Expert’s Baglihar decision (2007). Dulhasti Stage II from the CEA and NHPC; Kirthai II’s developer from the CEA. Pondage figures for the other run-of-river projects are not published.

ProjectRiverMWStatusType And StorageBuilt By
SalalChenab690RunningRun-of-riverNHPC
BagliharChenab900RunningRun-of-river; pondage 32.56 million m³, about 0.03 MAFJKSPDC
DulhastiChenab390RunningRun-of-riverNHPC
Pakal DulMarusudar1,000Being built, 82%, due December 2026Storage; about 108 to 109 million m³, about 0.09 MAFNHPC joint venture
KiruChenab624Being built, 85.5%, due December 2026Run-of-riverNHPC joint venture
KwarChenab540Being built, 35%, due March 2028Run-of-riverNHPC joint venture
RatleChenab850Being built, 30%, due November 2028Run-of-riverNHPC joint venture
SawalkotChenab1,856Awaiting final approvalRun-of-river, limited pondageNHPC
Kirthai IChenab390Under examinationRun-of-riverNot stated
Kirthai IIChenab930Concurred by the CEARun-of-river, limited pondageNHPC joint venture (CVPPL)
Dulhasti Stage IIChenab260Approved by the CEA (May 2025); environmental clearance January 2026Run-of-riverNHPC
BursarMarusudar800Survey and investigationStorage (figure not published)NHPC
Reoli DugliChenab, Himachal456In SJVN’s pipelineNot publishedSJVN
Sach KhasChenab, Himachal287In SJVN’s pipelineNot publishedSJVN
PurthiChenab, Himachal234In SJVN’s pipelineNot publishedSJVN
BardangChenab, Himachal166In SJVN’s pipelineNot publishedSJVN
KishangangaKishanganga (Jhelum basin)330RunningRun-of-riverNHPC
Uri IJhelum480RunningRun-of-riverNHPC
Uri IIJhelum240RunningRun-of-riverNHPC
Nimoo BazgoIndus45RunningRun-of-riverNHPC
ChutakSuru (Indus basin)44RunningRun-of-riverNHPC
How It Unfolded
19 Sep 1960India and Pakistan sign the Indus Waters Treaty.
1987Work on the Tulbul barrage stops after Pakistan objects.
23 Apr 2025India holds the treaty in abeyance after the Pahalgam attack.
15 May 2026A Court of Arbitration issues an award on pondage at Kishanganga and Ratle. India rejects it.
Jul 2026Bids open for NHPC’s Chenab-Beas tunnel works.
31 Aug 2026The court says the treaty remains in force and limits concreting at Ratle. India rejects it the same day.
Dec 2026Pakal Dul and Kiru are due to be completed.
Sources And MethodShow

Ministry of External Affairs: Foreign Secretary’s briefing of 23 April 2025 (treaty in abeyance); statements of 16 May 2026 and 31 August 2026 rejecting the Court of Arbitration (as reported by ANI and The Federal). Permanent Court of Arbitration press release, Indus Waters Western Rivers Arbitration, 31 August 2026 (award and interim measures on Ratle). Lok Sabha, unstarred question 42, 22 November 2012 (western rivers 135.6 MAF, eastern rivers 32.8 MAF). NHPC project pages (capacities and status of Salal, Dulhasti, Uri I and II, Kishanganga, Nimoo Bazgo, Chutak, Ratle, Pakal Dul, Kiru, Kwar, Sawalkot). JKSPDC and Tractebel (Baglihar, 900 MW). Government of India PAIMANA progress report, as reported by the Daily Excelsior, 5 July 2026 (physical progress and target dates). Daily Excelsior, 3 September 2026 (Sawalkot approvals). Swarajya, 22 May 2026, Outlook India, 21 July 2026, and NHPC’s tender notice (Chenab-Beas link tunnel and Salal bypass tunnel). CEA approval record and NHPC (Dulhasti Stage II; Kirthai II developer). ThePrint, 26 June 2025 (Jal Shakti Minister on the Tulbul project). Power Minister Manohar Lal’s briefing of 10 June 2025, as reported by The Indian Express (Pakal Dul storage of about 109 million cubic metres, and Greater Kashmir, 13 July 2025, about 108 million cubic metres; Sawalkot, Kirthai and Dulhasti Stage II run-of-river; Bursar storage). Neutral Expert’s Baglihar decision, 12 February 2007 (pondage of 32.56 million cubic metres). Lok Sabha answer of the Ministry of Power, December 2025 (the four projects under construction). SJVN Annual Report 2025-26 (Reoli Dugli, Sach Khas, Purthi, Bardang). MAF figures converted at 1 MAF = 1,233.5 million cubic metres. Boundary: Survey of India via DataMeet; UT line from the Survey of India map of 2 November 2019 via DataMeet. PoK: Natural Earth, approximate. Rivers: Natural Earth and OpenStreetMap contributors (ODbL), fetched 2 November 2026. Project sites: OpenStreetMap and Wikidata, approximate; Sawalkot and Tulbul placed at the nearest named point.